CPC announces planned 45-day shutdown of Sapugaskanda refinery

March 1, 2024 at 4:54 PM

The Sapugaskanda Oil Refinery will cease operations for 45 days in early July 2024, more than 03 years since the previous turnaround (TAR) in February 2021, the Ceylon Petroleum Corporation (CPC) announced today. 

Issuing a statement, the CPC said that this is a mandatory requirement, in compliance with international norms, that qualifies the refinery for safe and reliable operation for a further 03 years.

Once the refinery is brought back on stream after the Turnaround, it will be subjected to upgrades designed to increase its contribution to Sri Lanka’s changing product requirements. 

The CPC said during the scheduled shutdown, it will maintain a full capacity of crude to regain full throughput in the shortest possible time, along with a buffer stock of products for approximately twice the planned shutdown period to ensure continuous supply to customers. (NewsWire)